SFMTA:
Taraval Street Repaving Coming Up Soon
As the L Taraval Improvement Project is nearing completion, street repaving is scheduled to begin on March 15 and continue for approximately a couple of weeks. During construction, temporary street closures and parking restrictions will apply where the work is occurring.
Work sequence: Paving will start on the south side of Taraval from 46th Avenue toward Sunset Blvd. from March 15 to 18, and then switch to the north side in reverse direction from March 18 to 24.
Work hours: Monday through Friday approximately from 8 a.m. to 5 p.m.
Noise control: Measures will be taken to minimize the noise disruption; however neighbors close to the job site can hear some noise from construction vehicles.
L Bus Reroute: To accommodate the paving and street repair work, the L Taraval bus will be rerouted onto Ulloa Street in both directions between 35th and 46th avenues. The bus reroute will be effective on March 8 due to the street base repair work that has to be done prior repaving. The alternate bus stops located on Ulloa Street are parallel to the stops on Taraval Street.
L Taraval Bus Reroute to Ulloa Street affecting five stops in each direction:
Missed Stops on Taraval toward Downtown | Replacement Stops on Ulloa toward Downtown |
46th Ave., southwest corner | 46th Ave., southwest corner |
44th Ave., southwest corner | 44th Ave., southwest corner |
42nd Ave., southwest corner | 42nd Ave., southwest corner |
40th Ave., southwest corner | 40th Ave., southwest corner |
Sunset Blvd., southwest corner | Sunset Blvd., southwest corner |
Missed Stops on Taraval toward Ocean | Replacement Stops on Ulloa toward Ocean |
Sunset Blvd., northeast corner | Sunset Blvd., northeast corner |
40th Ave., northeast corner | 40th Ave., northeast corner |
42nd Ave., northeast corner | 42nd Ave., northeast corner |
44th Ave., northeast corner | 44th Ave., northeast corner |
46th Ave., northeast corner | 46th Ave., northeast corner |
Substantial Completion: After the street paving, the project will soon reach substantial completion, which means the major infrastructure work is done. Following that, more work is required to fully complete the project which includes testing of the tracks with trains, landscape and streetscape work. The Segment A of the project will be fully completed in the summer of this year.
Thank you: The SFMTA would like to thank the neighbors and local merchants for their patience and understanding while we are making improvements to Taraval Street.
For more information, visit SFMTA.com/TaravalProject
Categories: Press Release