Press Release: SFMTA L-Taraval Project Work Schedule for Aug. 26-Sept. 6, 2019

Forecast of Work Planned for August 26-September 6

Excavation of small exploratory holes to verify the locations of existing underground utilities is planned for August 26-30.

Sewer main replacement is planned for August 26-30 and September 3-6.

Two large manholes will be constructed as part of the sewer mainline work.

What to Expect: 

Excavation requires jackhammering of the pavement. Dust control measures will be in place to prevent dust kick up from the work.

Location and Time of Work:

North side of Taraval Street between 46th and 45th avenues

Monday to Friday 7 a.m-5:00 p.m

No work on Labor Day: Sept. 2, 2019

Traffic Impacts:

Some parking will be temporarily restricted in construction zones and traffic lanes will be modified in the northbound lane during active work.

Muni Customer Impacts: 

The following bus stops are planned to be temporarily relocated during construction work hours. Look for “Board Here” signs nearby:

From Aug.t 29 to September 26, inbound Muni 18 bus stop at 46th Avenue and Taraval will be relocated to 46th Avenue and Santiago.

From Aug. 29 to Sept. 19, inbound L-Owl bus stop at Taraval and 46th Avenue will be relocated to Taraval and 45th Avenue

The following two-week construction forecast is subject to change due to weather delays or unexpected field conditions.

Questions or concerns? Contact us at Jerri.Diep@SFMTA.com or 415.646.2382

 

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s